2024 Bond

2024 Crestwood Bond Logo

2024 Bond Update - February 2025 (#1)

Planning Phase (Fall 2024 - Summer 2025):

  • Elementary Schools: Finalizing plans for additions, renovations, playgrounds, and fencing.

  • Riverside MS: Designing parking lot traffic flow.

  • Crestwood HS: Initial planning for field house, fields, and classroom addition.

Abatement (Summer 2025):

  • Hillcrest, Highview, and Kinloch Elementary Schools prepared for renovations.

Project Timeline:

  • Phase 1 (Late Summer 2025 - Fall 2026): Elementary and playground projects; Riverside MS parking expansion.

  • Phase 2 (Fall 2026 - Fall 2029): Middle and high school additions and renovations.

  • Phase 3 (Fall 2027 - 2028): Early Childhood Center and Transportation Building.

Next Steps:

  • Finalize designs, confirm project scopes, and keep the community informed.

Together, we are building the future for Crestwood Schools.

2024 Bond - Original Information

WHAT WOULD THE BOND DO?

  • Air Conditioning

  • Roofing & HVAC Upgrades

  • Electrical & Plumbing Upgrades

  • Structural Upgrades as Needed

  • Technology Upgrades

  • Security & Safety Upgrades

  • Furniture Upgrades